WYDOT says Etna North project ready to move ahead

JACKSON, Wyo. — The Wyoming Department of Transportation (WYDOT), along with contract crews from Avail Valley Construction, will be continuing work on US 89 between Thayne and Alpine Junction this summer.

The contractor has been clearing and grubbing throughout the project limits, as well as windrowing topsoil along the new right-of-way. A permanent fence is also being installed throughout the project.

WYDOT and contract crews are planning to begin moving dirt for the road widening, as well as installing pipe, starting at the south end of the project and working north. There will be limited delays during this work and most of the activity will be being done on the shoulders of the roadway. The widening work is tentatively scheduled to be completed in August.  After the widening is complete, crews will begin milling operations.  Paving of the roadway is expected to be completed this fall.

WYDOT asks that motorists remember to obey all roadside signs, flaggers, and traffic control devices to maintain safety for the traveling public as well as crews working in the area. Background information about the project is available online.

The Etna North Project was awarded to Avail Valley Construction, out of Afton, for $19,740,740.  The project involves grading, draining, placing crushed base and bituminous pavement surfacing, full-depth reclamation and miscellaneous work on approximately 9.30 miles on US 89 beginning at mile marker 108.13 between Thayne and Alpine Junction. The completion date for this project is June 30, 2022.

About The Author

Buckrail @ Jacob

Jacob Gore was born and raised in Cheyenne, the capital city of Wyoming. As a proud Wyomingite, he loves to share his home with visitors from around the world. Spending years in Jackson and Alaska as an interpretive nature guide, he remains a photographer, traveler, storyteller, and avid hobbyist of all-things outdoors. Jacob enjoys bridging the connection between Jackson and the rest of the state.

You May Also Like
News
Car accident in Snake River Canyon injures one
Community
WYDOT: Truck arrestor functioning after recent use
Road Work
WYDOT: Expect delays on sections of Fall Creek Road in coming weeks
Housing
Housing in Jackson: ripple affects in neighboring communities
News
Moose-Wilson Road to close on June 15
Road Work
WYDOT: Work on Flat Creek Bridge to resume at night