JACKSON, Wyo. — Hooray!
After a long construction season and frequent road access changes, Gregory Lane is fully open for the entire length of the road. Drivers can once again make it from South Park Loop Road to High School Road using the upgraded street. Buckrail photographer Nick Sulzer dropped by to see the situation on Monday after the Town of Jackson’s Engineering Division shared the good news on Friday evening.

The Town’s largest-ever public works project broke ground in May of 2025 after being in the works for more than 20 years. In 2019, $8.5 million in SPET funding was allocated to the Gregory Lane project to address street, stormwater and sewer infrastructure.
The renovation plan included the addition of stormwater treatment systems, streetlights throughout the corridor, 6,350 feet of new stormwater pipes, 6,400 feet of new curb and gutter, 3,611 feet of new water main pipes, 3,700 feet of new sewer main pipes and 19,200 square feet of sidewalk.

While the road is fully usable again, the project is not 100% complete quite yet.
This week, Evans Construction is removing traffic control devices, cleaning out the staging area and hauling materials away. If weather allows, crews will bring manholes and valves to the street surface, install street signage, stripe roads, install lighting, and potentially pour more red brick stamped concrete.
Many of those tasks are likely to be picked back up in the spring, per the announcement.

“Expect a reduced presence of construction crews and equipment as we clean up and demobilize,” the department’s announcement states. “Please go slow and share the road.”
When work resumes in 2027, crews will build elevated pathway crossings, stamp red brick concrete in the sidewalk buffer zone and complete landscaping.