JACKSON, Wyo. — Gregory Lane projects will likely continue through November, and the Town of Jackson (TOJ) reminds residents that businesses along the street remain open.
According to a press release, as of May 20 construction consists of the installation of sewer main pipes through the intersection with Martin Lane, along with manhole installation and a concrete curb and sidewalk along the south end of Gregory Lane.

The TOJ reminds residents that access will continue to shift along Gregory Lane as construction moves north. Property owners will be notified of changes. Additionally, the TOJ recommends sharing updates among friends and neighbors.
Rebuilding and remodeling the Gregory Lane area received the lion’s share of its funding — $8.5 million — from the 2019 Specific Purpose Excise Tax (SPET). The project has also received funding from the 2022 SPET.