JACKSON, Wyo. — Gregory Lane projects will likely continue through November, and the Town of Jackson (TOJ) reminds residents that businesses along the street remain open.

According to a press release, as of May 20 construction consists of the installation of sewer main pipes through the intersection with Martin Lane, along with manhole installation and a concrete curb and sidewalk along the south end of Gregory Lane.

Updated current closures and access on Gregory Lane. Image: TOJ

The TOJ reminds residents that access will continue to shift along Gregory Lane as construction moves north. Property owners will be notified of changes. Additionally, the TOJ recommends sharing updates among friends and neighbors.

Rebuilding and remodeling the Gregory Lane area received the lion’s share of its funding — $8.5 million — from the 2019 Specific Purpose Excise Tax (SPET). The project has also received funding from the 2022 SPET.

Hannah is a Buckrail Staff Reporter and freelance web developer and designer who has called Jackson home since 2015. When she’s not outside, you can probably find her eating a good meal, playing cribbage, or at one of the local yoga studios. She’s interested in what makes this community tick, both from the individual and collective perspective.