JACKSON, Wyo. — As the school year draws closer, and cool morning temps signal an imminent change in seasons, Buckrail checked in with the Town of Jackson (TOJ) to see how construction on Gregory Lane is progressing.
The construction crews have been alternating work on the three utilities that are being replaced: sewer, water and stormwater. TOJ Public Works Director Johnny Ziem told Buckrail that the sewer system is currently nearing the final stretch on the north end, from V-O Lane to the connection with South Park Loop Road. Water pipes and stormwater will then be installed and connected to the same intersection. Within the next seven to 10 days, paving will take place from Berger Lane, north through the S-curve, not quite to V-O Lane. The crew will also begin prepping for sidewalks, and getting the curb and gutter in place.
“We’re, in essence, rebuilding the entire road; putting a new curb and gutter, sidewalk, streetlights, and then three major utilities,” Ziem explained. “It’s time consuming. It’s impactful to the community because it takes so long, but we’re excited because … we’ve been talking about this project for a long, long time. It’s very much needed.”
Originally slated to be finished in two construction seasons, the completion date could end up hinging on autumn weather. Ziem said the original goal still remains, and that managers are feeling pretty confident. But Jackson weather in October and November has the potential to put a damper on plans. Last year, unseasonable weather allowed work to continue deep into fall, with paving and striping completed by Nov. 20. Ziem said that just over half the project was left to complete when construction began this year in April.
The project is still within its allotted budget, due to planners accounting for unknowns ahead of time. More water interruptions to businesses and residences in the area are likely, though Ziem said that if they are working on a major water connection, they try to complete it at night for the least impact. TOJ has remained in close contact with the Teton County School District about access to the school bus barn. Ziem noted that major changes are not anticipated, and bus drivers will be able to use the south end of Gregory Lane.
Ziem urges drivers to keep an eye on signage and closures surrounding the construction area. He said there is coordination with businesses regarding deliveries and other access, and that drivers should pay attention to which end of the street has a route to their destination.
“Any road that we dig up, there’s so many considerations for us and our contractors when it comes to safety and all that stuff,” Ziem said. “We’re happy that the community supported the project and still supports the project and understands what we’re trying to do. And we’re trying to do it as quickly and efficiently as possible.”